Debt recovery / Construction

Your customer refuses to pay for extra work

YES you can get paid for every extra they asked for, if you put it in a payment claim and make them answer it. If they don't answer within 10 business days, they owe the lot. Do it this month, before they rewrite history.
Corporate Recovery Partners
Your customer refuses to pay for extra work - debt recovery guidance from Corporate Recovery Partners
01 / 06

Where you stand

They asked for the changes. You did the work. You paid for the labour and materials. Now the invoice lands and suddenly nobody remembers asking.

This is one of the oldest tricks on a job site. Ask for extras on the run, take the benefit, then refuse to pay because "it was never agreed" or "it was part of the original price". They are counting on you having no paperwork and no stomach for a fight.

You have both. Let's use them.

02 / 06

Your weapons

Your first weapon is the Security of Payment Act. In Victoria, you are entitled to progress payments for construction work you carry out under the contract. If the contract doesn't set the value of the work, it is valued having regard to the contract price, the rates in the contract and any variation the parties agreed to. A variation is a change in the scope of the work under the contract.

Victoria's old limits on "claimable variations" are gone. Sections 10A and 10B were repealed by the 2025 amending Act, and that repeal has been in force since 15 April 2026.

Serve a payment claim that identifies the extra work, states the amount and says it is made under the Act. If they don't answer with a payment schedule within 10 business days, or sooner if the contract says so, they are liable for the full claimed amount. If they don't pay by the due date, you can sue for it as a debt or go to adjudication. You can also give notice and suspend work. Three business days after that notice, you can down tools.

If the debt is $4,000 or more, due and payable and not genuinely disputed, a statutory demand under the Corporations Act gives a company 21 days to pay or go to court.

03 / 06

How to make sure you can

Yes you can, if the variation is locked down. Here is how to make sure you can.

Gather every scrap of proof the change was asked for: emails, texts, site diary notes, marked-up drawings, photos and delivery dockets. Match each item of extra work to the instruction that started it.

Price it using the contract rates where they exist. Then put it in your next payment claim. Don't leave extras sitting on a separate invoice they can ignore.

For the next job, put a variation clause in your contract. No extra work starts without a written instruction, a price and their sign-off, even if it is a text message.

04 / 06

What happens if you wait

Waiting is how variations die. Memories fade, site managers change jobs and the "verbal OK" becomes your word against theirs.

The clock runs against you too. A Victorian payment claim generally can't be served later than six months after practical completion, unless the contract allows later. Miss that window and your fastest weapon is gone.

Every week you leave it, you are funding their project out of your own pocket.

05 / 06

Act now — go to war and get your money

1. Today, list every variation, the date it was asked for, who asked and the price. 2. Attach the proof to each line: the text, the email, the photo, the docket. 3. Serve a payment claim under the Security of Payment Act that includes every variation. 4. If no payment schedule arrives in time, move straight to recovery for the full amount. 5. Send the file to CRP. We will go after every dollar for every change they asked for.

You have a crisis. Let's go to war and fix it.

06 / 06

Sources

Victorian Legislation — Building and Construction Industry Security of Payment Act 2002 (ss 4, 9, 11, 14, 14C, 15, 16, 29, 54): https://www.legislation.vic.gov.au/in-force/acts/building-and-construction-industry-security-payment-act-2002

NSW Government — Making a payment claim: https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/making-a-payment-claim

Federal Register of Legislation — Corporations Act 2001 (ss 459E, 459H): https://www.legislation.gov.au/C2004A00818/latest/text

Source: Victorian Legislation — Building and Construction Industry Security of Payment Act 2002 (ss 4, 9, 11, 14, 14C, 15, 16, 29, 54)