Unused materials can hide inside a troubled job’s cost to finish

Reconcile physical stock, existing orders and remaining scope on a loss-making project to avoid duplicate procurement assumptions.
Corporate Recovery Partners
CRP Natalie avatar beside CHECK WHAT IS ON SITE and Count usable stock before ordering the same items again.
Separate confirmed materials from hoped-for savings. on a monochrome 1609 cover.
01 / 06

The estimate and the site can tell different stories

A troubled job's revised budget may include materials that are already on site or already ordered. It may also assume stock is available when it has been damaged, used elsewhere or never delivered. Before accepting the next cost-to-finish figure, compare the remaining scope with the physical materials and purchase commitments the business can verify.

02 / 06

Count what can actually be used

Ask a suitable site person to identify the significant remaining materials by specification, quantity and condition. Match them to the work still required. Do not call everything in the storage area available stock. Some items may belong to another party or be allocated elsewhere, so check ownership and contractual restrictions before planning any transfer or use.

03 / 06

Reconcile the paperwork with the count

Business.gov.au's record-keeping guidance includes records of expenses associated with stock. Compare delivery records, supplier invoices and open purchase orders with the site count. Note discrepancies rather than forcing the figures to agree. A supplier invoice proves a charge was raised; it does not establish that every item is sitting on site ready for the remaining work.

Source: business.gov.au: Record keeping

04 / 06

Avoid ordering the same requirement twice

Imagine a hypothetical contractor budgeting for forty fixtures to complete a project. Twelve matching fixtures are verified on site and ten more appear on an open order awaiting confirmation. The team needs to investigate the order before placing another purchase for all forty. The example does not assume that every listed item is usable or that an existing order can be cancelled.

05 / 06

Only count confirmed savings

If surplus stock might be returned, ask the supplier about actual terms and charges. Do not reduce the forecast by a hoped-for refund before the position is clear. Likewise, include handling or transport needed to use materials stored elsewhere. A practical inventory review should improve the estimate without replacing one optimistic assumption with another.

06 / 06

Give the buyer an agreed requirement

Record the verified stock, confirmed incoming orders and remaining purchasing need in one dated schedule. Nominate who can change it when site conditions move. Feed the result into the project estimate and business cash view. This is a targeted check on procurement waste, not a reason to assume the rest of a loss-making project's difficulties have been resolved.