They say the invoice is wrong

Where you stand
You did the job. You sent the invoice. Now, weeks later, they tell you it's "wrong". No detail, no numbers, no fix. Just a reason not to pay.
It is a stall dressed up as a dispute. They are not confused. They are using your money to run their business. A customer with a real problem tells you what it is the day the invoice lands. A customer who says "it's wrong" and goes quiet is betting you will fold.
Every day the "dispute" drifts, they keep your cash and you carry their job. You don't fold. You make them prove it or pay it.
Your weapons
In construction, the Security of Payment Act is built for exactly this stall. In Victoria, once you serve a valid payment claim, they answer with a payment schedule or they owe the lot. If they want to pay less, the schedule must say why, and give their reasons for withholding payment.
If they don't serve a payment schedule within the time in the contract or 10 business days, whichever is earlier, they become liable for the full claimed amount. If they still don't pay by the due date, you can recover it as a debt in court or go to adjudication. In that court case they cannot bring cross-claims or raise defences about the contract. "The invoice is wrong" is dead on arrival. NSW is just as tough: miss the payment schedule and they are liable for the full amount, and in adjudication they cannot raise any reason they left out of the schedule.
Outside a payment claim, the Corporations Act gives you the statutory demand. If the debtor is a company and owes you $4,000 or more that is due and payable, it has 21 days to pay or go to court. The court sets a demand aside if there is a genuine dispute. A vague complaint with nothing behind it is not a dispute. It is a stall.
How to make sure you can
Yes you can get paid, if you strip the excuse bare. Here is how to make sure you can.
Write to them today. Demand a list of every line they say is wrong, the amount and the reason, by a fixed date. No list, no dispute. Say you will fix any genuine error straight away, and that the rest is due now.
Pull your file together: the quote or contract, purchase orders, approved variations, delivery dockets, timesheets and site photos. Match every disputed line to a document.
If part of the invoice isn't disputed, demand that part be paid now. No one gets to hold the whole amount over one line item.
Then fix your terms for the next job: a set time to raise invoice disputes in writing, interest on late payment and the right to stop work.
What happens if you wait
Waiting turns a stall into a real dispute. The longer you leave it, the more time they have to invent reasons and dig up "defects" nobody mentioned on site.
Deadlines run against you too. A Victorian payment claim must be served on time, and the latest date is generally six months after practical completion unless the contract allows later. Miss it and you lose your fastest weapon.
Act now — go to war and get your money
1. Today, send a written demand for the specific errors, with a 5 business day deadline. 2. Fix any genuine error immediately and reissue. Leave them nothing to hide behind. 3. On construction work, serve a payment claim stating it is made under the Security of Payment Act. 4. If no payment schedule comes back in time, move straight to recovery for the full amount. 5. Send the file to CRP. We will rip their excuse apart and go after your money.
You have a crisis. Let's go to war and fix it.
Sources
Victorian Legislation — Building and Construction Industry Security of Payment Act 2002 (ss 14, 14C, 15, 16): https://www.legislation.vic.gov.au/in-force/acts/building-and-construction-industry-security-payment-act-2002
NSW Government — Responding to a payment claim: https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/responding-to-a-payment-claim
Federal Register of Legislation — Corporations Act 2001 (ss 459E, 459G, 459H): https://www.legislation.gov.au/C2004A00818/latest/text