They paid half. Where's the rest?

Where you stand
They paid half and went quiet. Maybe they called it "a good-faith payment". Maybe they said nothing at all. Either way, they have decided what your work is worth, and they didn't ask you.
Half a payment is not progress. It is a customer testing how much they can get away with. Pay half, wait, see if you chase. If you don't, half becomes the deal.
You quoted the job. You did the job. You get paid for the whole job. Don't thank them for half. Bill them for the rest.
Your weapons
In construction, the Security of Payment Act was written for short payments. In Victoria, when you serve a payment claim, their payment schedule must say why they are paying less, and give their reasons for withholding.
If they schedule an amount and then don't pay it by the due date, you can recover the unpaid part as a debt in court or go to adjudication. In that court case they can't bring cross-claims or raise contract defences. If they serve no schedule at all, within the contract time or 10 business days, whichever is earlier, they owe the full claimed amount. NSW runs the same rule: miss the payment schedule and they are liable for the full amount, and in adjudication they can't raise reasons they left out of it.
You can roll the unpaid balance into your next payment claim. The Act lets you include any amount from an earlier claim that still hasn't been paid.
If the balance is $4,000 or more, due and payable and not genuinely disputed, a statutory demand under the Corporations Act gives a company 21 days to pay or go to court. Fail, and on a winding-up application within three months the court must presume it is insolvent.
How to make sure you can
Yes you can recover the balance, if you nail down exactly what is owed. Here is how to make sure you can.
Work out the numbers today: invoice total, amount paid, date paid and balance. Match the payment to the invoice so they can't later claim it was for something else.
Write to them confirming the payment received and the balance still due, with a due date. If they reply with a reason, you now have it in writing. If they don't, you have their silence on record.
Then fix your terms for the next job: progress claims, interest on late payment and the right to stop work if a claim is short-paid.
What happens if you wait
Waiting tells them the half was enough. Every week the balance sits, it looks more like a settled account and less like a debt.
Deadlines run too. A Victorian payment claim generally can't be served more than six months after practical completion unless the contract allows later. Miss it and your fastest weapon is gone.
And a customer who can only pay half today can be paying nothing tomorrow.
Act now — go to war and get your money
1. Today, calculate the exact balance and match every payment to its invoice. 2. Email them the balance, the due date and a request for their reasons in writing. 3. For construction work, serve a payment claim under the Security of Payment Act for the unpaid balance. 4. If they don't pay the scheduled amount, or don't schedule at all, go straight to recovery. 5. Send the file to CRP. We will go after the other half.
You have a crisis. Let's go to war and fix it.
Sources
Victorian Legislation — Building and Construction Industry Security of Payment Act 2002 (ss 14C, 14D, 15, 16, 17): https://www.legislation.vic.gov.au/in-force/acts/building-and-construction-industry-security-payment-act-2002
NSW Government — Responding to a payment claim: https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/responding-to-a-payment-claim
Federal Register of Legislation — Corporations Act 2001 (ss 459C, 459E, 459H): https://www.legislation.gov.au/C2004A00818/latest/text