The site may reopen but your crew is already committed elsewhere
Assess remobilisation instruction after stoppage against resources and changed costs without assuming suspension rights.
Corporate Recovery Partners
01 / 06
The restart message is tentative
A hypothetical subcontractor moves its crew to another job during a stoppage. The builder later says the original site may reopen on Monday and expects everyone back. Before promising immediate attendance, clarify the instruction and review the commitments made during the interruption. A possible restart date and an authorised, workable mobilisation plan are different things.
Ask the appropriate project representative about access, the work sequence and the required attendance. Keep the response and any formal instruction. Do not treat a rumour from another trade as confirmation that the site is ready. If safety or access arrangements are unresolved, raise them through the proper process rather than sending people to investigate informally.
Business.gov.au recommends clear contractual responsibilities and recording changes. Have the relevant suspension, programme and variation terms reviewed where necessary. The business should not assume it can refuse to return, demand any price it chooses or disregard existing commitments. Ask an adviser how the actual restart request and the earlier stoppage affect the obligations in this project.
In the hypothetical example, the crew's current job may have contractual commitments of its own. Identify labour, equipment and supplier availability and explain the practical constraints accurately. Avoid promising two customers the same resources for the same period. If alternatives are proposed, check competence, cost and approval requirements before representing them as confirmed capacity.
Separate remobilisation costs from agreed entitlement
Estimate transport, setup and other relevant restart costs with supporting information. Discuss any proposed adjustment through the appropriate contractual channel. Do not add a new amount to the invoice solely because the stoppage was inconvenient. Keep agreed changes distinct from disputed or unapproved costs and retain the communications showing what was requested and accepted.
Once the position is settled, provide the current instructions, sequence and responsible contacts to the people returning. CRP can help organise the commercial effects for review. A clear restart plan reduces the risk of a second dispute by aligning what the business promises with the work it is authorised and able to perform.